Table 39 : Sector-Wise Cost Overrun of Delayed Central Sector Projects (end-March)
(₹ Billion)
Sector / Year 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1. Atomic energy                              
a) Number of projects 0 1 0 0 1 1 3 3 3 3 4 3 4 4 4
b) Original estimate 0.00 34.47 0.00 0.00 3.43 3.43 165.86 204.56 208.76 177.69 380.56 369.50 404.42 404.42 404.42
c) Now anticipated 0.00 67.60 0.00 0.00 3.43 3.43 165.86 195.25 221.30 226.07 407.09 410.49 467.26 519.18 519.18
d) Cost overrun 0.00 33.13 0.00 0.00 0.00 0.00 0.00 -9.31 12.54 48.38 27.00 41.00 62.84 114.76 114.76
2. Civil aviation                              
a) Number of projects 0 0 0 0 1 1 0 2 7 3 3 3 3 5 1
b) Original estimate 0.00 0.00 0.00 0.00 1.92 1.92 0.00 2.46 28.23 24.20 25.88 25.88 9.89 16.59 3.09
c) Now anticipated 0.00 0.00 0.00 0.00 1.92 1.92 0.00 2.46 28.23 24.20 29.70 29.70 10.42 17.12 3.09
d) Cost overrun 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 4.00 0.53 0.53 0.00
3. Coal                              
a) Number of projects 3 3 2 1 1 1 1 8 24 10 19 28 30 37 42
b) Original estimate 19.75 19.75 3.84 2.00 2.00 2.00 2.87 67.51 126.89 58.51 137.91 242.63 262.41 283.02 239.87
c) Now anticipated 20.10 19.93 5.69 1.83 1.83 1.83 2.87 83.66 139.62 75.41 151.02 261.37 364.35 323.10 253.08
d) Cost overrun 0.35 0.18 1.85 -0.17 -0.17 -0.17 0.00 16.15 12.73 16.90 13.00 19.00 101.94 40.08 13.22
4. Finance                              
a) Number of projects 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
b) Original estimate 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
c) Now anticipated 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
d) Cost overrun 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5. Fertilisers                              
a) Number of projects 1 1 1 1 0 0 0 0 0 1 2 1 0 0 0
b) Original estimate 3.50 3.50 3.50 3.50 0.00 0.00 0.00 0.00 0.00 14.79 7.63 14.79 0.00 0.00 0.00
c) Now anticipated 5.09 5.09 5.09 6.10 0.00 0.00 0.00 0.00 0.00 14.79 7.63 14.79 0.00 0.00 0.00
d) Cost overrun 1.59 1.59 1.59 2.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6. Mines                              
a) Number of projects 1 1 1 0 0 0 0 0 1 1 0 0 0 0 0
b) Original estimate 20.62 20.62 20.62 0.00 0.00 0.00 0.00 0.00 40.92 40.92 0.00 0.00 0.00 0.00 0.00
c) Now anticipated 20.62 20.62 20.62 0.00 0.00 0.00 0.00 0.00 40.92 44.02 0.00 0.00 0.00 0.00 0.00
d) Cost overrun 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.10 0.00 0.00 0.00 0.00 0.00
7. Steel                              
a) Number of projects 1 1 1 1 4 6 7 14 20 7 10 15 13 17 15
b) Original estimate 4.31 2.99 2.99 1.07 7.73 16.09 102.68 227.32 394.30 302.80 510.99 646.98 642.08 563.71 390.95
c) Now anticipated 4.50 2.99 2.99 1.70 7.73 16.78 102.73 271.11 461.20 397.80 571.58 708.56 701.62 599.40 396.01
d) Cost overrun 0.20 0.00 0.00 0.63 0.00 0.69 0.05 43.79 66.90 95.00 61.00 62.00 59.54 35.69 5.05
8. Petro-chemicals                              
a) Number of projects 0 0 0 0 0 0 0 0 0 0 0 1 0 1 0
b) Original estimate 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 54.61 0.00 54.61 0.00
c) Now anticipated 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 89.20 0.00 98.34 0.00
d) Cost overrun 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.00 0.00 43.73 0.00
9. Petroleum                              
a) Number of projects 4 8 12 13 13 24 20 26 41 27 38 39 50 43 38
b) Original estimate 27.03 99.48 136.52 159.82 240.85 355.60 294.57 464.29 864.00 375.62 1071.98 1117.43 1394.93 885.33 479.95
c) Now anticipated 26.25 110.30 150.10 193.58 296.92 455.25 368.71 566.35 1110.51 401.05 1154.27 1218.38 1537.59 1016.35 499.99
d) Cost overrun -0.78 10.82 13.57 33.76 56.07 99.65 74.14 102.06 246.51 25.42 82.00 101.00 142.65 131.02 20.04
(Continued)

TABLE 39 : SECTOR-WISE COST OVERRUN OF DELAYED CENTRAL
SECTOR PROJECTS (End-March) (Concld.)
(₹ Billion)
Sector / Year 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
10. Power                              
a) Number of projects 12 11 12 15 20 12 28 28 33 40 50 53 44 63 64
b) Original estimate 114.46 99.85 78.72 69.63 189.00 269.73 522.13 686.00 827.71 1055.69 1377.66 1356.56 1244.90 1649.42 1716.22
c) Now anticipated 281.77 240.06 215.45 168.12 282.20 279.03 543.32 721.40 862.54 1102.20 1522.67 1504.92 1421.72 1932.66 2088.30
d) Cost overrun 167.31 140.21 136.73 98.49 93.20 9.30 21.19 35.40 34.83 46.31 145.00 148.00 176.81 283.23 372.08
11. Railways                              
a) Number of projects 20 24 28 23 19 19 22 44 53 31 34 41 37 35 31
b) Original estimate 66.90 80.36 92.82 86.34 89.92 89.52 97.58 158.71 193.88 225.32 236.71 279.24 285.89 290.92 367.14
c) Now anticipated 103.37 124.72 140.43 136.12 172.96 178.23 210.85 400.72 405.23 437.74 560.68 735.37 730.22 862.53 904.32
d) Cost overrun 36.47 44.36 47.60 49.78 83.05 88.71 113.27 242.01 211.35 212.42 324.00 456.00 444.32 571.60 537.18
12. Surface transport                              
a) Number of projects 6 44 53 62 65 82 131 139 143 109 93 95 23 104 128
b) Original estimate 8.98 106.57 125.84 167.77 182.44 227.12 349.72 400.07 485.32 390.92 402.72 549.50 88.43 770.42 884.02
c) Now anticipated 18.10 113.63 134.27 170.45 183.60 234.04 357.89 406.43 489.46 404.90 431.72 581.95 110.95 789.83 908.42
d) Cost overrun 9.12 7.06 8.44 2.68 1.16 6.92 8.17 6.37 4.14 13.99 29.00 32.50 22.53 19.41 24.40
13. Telecommunication                              
a) Number of projects 0 0 1 5 21 23 18 22 35 35 9 5 4 2 2
b) Original estimate 0.00 0.00 1.47 16.01 60.26 79.78 71.53 75.13 140.69 166.28 38.56 29.35 20.18 7.21 154.45
c) Now anticipated 0.00 0.00 1.47 14.23 55.63 73.99 71.77 69.47 143.91 171.39 40.35 27.61 18.43 7.21 153.45
d) Cost overrun 0.00 0.00 0.00 -1.78 -4.63 -5.79 0.24 -5.66 3.22 5.11 2.00 -1.74 -1.75 0.00 -1.00
14. Others                              
a) Number of projects 1 1 1 4 4 2 1 1 6 4 2 1 1 17 18
b) Original estimate 48.60 48.60 48.60 55.44 55.44 6.14 5.43 5.43 91.11 157.28 69.38 63.95 24.94 826.62 648.08
c) Now anticipated 88.00 88.00 105.71 123.32 123.32 14.92 11.87 11.87 103.15 318.72 127.96 116.09 24.94 826.62 721.18
d) Cost overrun 39.40 39.40 57.11 67.88 67.88 8.78 6.44 6.44 12.04 161.44 58.58 52.14 0.00 0.00 73.10
Total                              
a) Number of projects 49 95 112 125 149 171 231 287 366 271 264 285 209 328 343
b) Original estimate 314.15 516.19 514.93 561.59 832.99 1051.33 1612.37 2291.48 3401.81 2990.02 4259.98 4750.42 4378.08 5752.27 5288.20
c) Now anticipated 567.80 792.94 781.82 815.46 1129.54 1259.41 1835.87 2728.72 4006.07 3618.29 5004.67 5698.43 5387.49 6992.34 6447.03
d) Cost overrun 253.66 276.74 266.89 253.88 296.55 208.08 223.51 437.24 604.26 628.27 745.58 948.90 1009.41 1240.07 1158.83
Notes : 1. Data relate to central sector projects costing ₹ 1 billion and above up to 2010. From 2011 onwards data pertain to projects costing ₹ 1.5 billion and above.
2. Projects without date of commissioning are not considered.
3. Cost overrun is taken as the difference between the 'anticipated cost' and the 'original cost'.
Source : Ministry of Statistics and Programme Implementation, Government of India.