Skip to main content
Not Pressed
Not Pressed
Pressed
Not Pressed
Not Pressed
Pressed
Not Pressed
Change Language
हिंदी
Search the Website
Search
Home
About Us ▼
About Us
Organisation & Functions
▶
Organisation Structure
Departments
Offices
Training Establishment
▶
College of Agricultural Banking
Reserve Bank Staff College
College of Supervisors
RBI's Functions and Working
Governors
Deputy Governors
Executive Directors
Media Kit
Communication Policy of RBI
Sources of Information
▶
Annual Publications
Half-yearly Publications
Quarterly Publications
Monthly Publications
Weekly Publications
Occasional Publications
SDDS
NSDP
Data Releases
Publications available on Subscription
General Information
RBI History
Museum
▶
The RBI Museum
RBI Monetary Museum
Notification ▼
Notifications
Master Directions
Master Circulars
Amendment Directions
Draft Notifications/Guidelines
▶
Draft Notifications/Guidelines
Draft Directions (RE-wise)
Index To RBI Circulars
Standalone Circulars
Circulars Withdrawn
Press Releases
Speeches & Media Interactions ▼
Speeches
Media Interactions
Memorial Lectures
Podcasts
Publications ▼
Biennial
Annual
Half-Yearly
Quarterly
Bi-monthly
Monthly
Weekly
Occasional
Reports
Working Papers
Legal Framework ▼
Act
Rules
Regulations
Schemes
Research ▼
External Research Schemes
RBI Occasional Papers
Working Papers
RBI Bulletin
History
DRG Studies
KLEMS
State Statistics and Finances
Statistics ▼
Data Releases
Database on Indian Economy
Public Debt Statistics
Regulatory Reporting ▼
List of Returns
Data Definition
Validation rules/ Taxonomy
List of RBI Reporting Portals
FAQs of RBI Reporting Portals
Home
Publications
Annual
Handbook of Statistics on Indian Economy
Publications
(
29 kb
) or
(
13 kb
)
Date : Aug 31, 2004
Table 35 : Sector-Wise Cost Overrun of Delayed Central Sector Projects
(Rupees crore)
Sector
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
1
2
3
4
5
6
7
8
9
10
11
1.
Atomic energy
a)
Number of projects
7
6
5
5
3
3
0
0
1
0
b)
Original estimate
3020.7
2638.2
2439.3
2455.6
1937.8
1937.8
0
0
3447.1
0
c)
Now anticipated
6464.8
5004.0
4904.0
5041.3
5713.7
5713.7
0
0
6760.0
0
d)
Cost overrun
3444.0
2365.7
2464.6
2585.7
3775.9
3775.9
0
0
3312.9
0
2.
Civil aviation
a)
Number of projects
1
3
3
2
2
0
0
0
0
0
b)
Original estimate
210.0
1431.8
1431.8
294.1
294.1
0
0
0
0
0
c)
Now anticipated
351.9
1667.1
1703.9
566.2
566.2
0
0
0
0
0
d)
Cost overrun
141.9
235.3
272.1
272.1
272.1
0
0
0
0
0
3.
Coal
a)
Number of projects
5
11
13
15
16
15
8
3
3
2
b)
Original estimate
705.8
2935.9
4060.1
6279.9
8320.8
7191.9
5356.2
1975.0
1975.0
384.4
c)
Now anticipated
1505.2
5075.7
6207.5
7722.7
9925.1
8686.2
6348.2
2010.3
1992.5
569.0
d)
Cost overrun
799.4
2139.8
2147.4
1442.8
1604.3
1494.3
992.0
35.3
17.5
184.6
4.
Finance
a)
Number of projects
1
1
1
1
1
1
1
0
0
0
b)
Original estimate
118.3
118.3
118.3
118.3
118.3
118.3
118.3
0
0
0
c)
Now anticipated
348.8
348.8
348.8
348.8
348.8
348.8
301.8
0
0
0
d)
Cost overrun
230.5
230.5
230.5
230.5
230.5
230.5
183.5
0
0
0
5.
Fertilisers
a)
Number of projects
2
3
3
1
0
0
0
1
1
1
b)
Original estimate
1578.4
2565.7
2093.2
618.4
0
0
0
350.0
350.0
350.0
c)
Now anticipated
1578.4
2565.7
2195.4
642.4
0
0
0
509.4
509.4
509.4
d)
Cost overrun
0
0
102.2
23.9
0
0
0
159.4
159.4
159.4
6.
Mines
a)
Number of projects
0
0
0
0
0
1
1
1
1
1
b)
Original estimate
0
0
0
0
0
157.5
157.5
2062.0
2062.0
2062.0
c)
Now anticipated
0
0
0
0
0
157.5
183.6
2062.0
2062.0
2062.0
d)
Cost overrun
0
0
0
0
0
0
26.1
0
0
0
7.
Steel
a)
Number of projects
3
2
3
5
4
3
1
1
1
1
b)
Original estimate
4243.2
3818.0
5443.8
6511.1
5154.1
2693.1
430.5
430.5
298.7
298.7
c)
Now anticipated
9427.9
8951.2
11167.9
13498.8
8856.7
3787.7
466.7
450.0
298.7
298.7
d)
Cost overrun
5184.7
5133.2
5724.2
6987.7
3702.6
1094.6
36.2
19.5
0
0
8.
Petro-chemicals
a)
Number of projects
0
2
3
3
1
1
0
0
0
0
b)
Original estimate
0
336.4
3820.7
3820.7
3484.4
3484.4
0
0
0
0
c)
Now anticipated
0
336.4
3841.4
3852.6
3809.0
3809.0
0
0
0
0
d)
Cost overrun
0
0.0
20.6
31.8
324.6
324.6
0
0
0
0
9.
Petroleum
a)
Number of projects
11
10
13
17
22
17
1
4
8
12
b)
Original estimate
9669.9
7594.3
16602.1
18890.6
20238.6
15905.4
133.6
2702.7
9948.3
13652.3
c)
Now anticipated
11892.0
9941.9
18169.4
20715.9
22058.1
16899.1
118.1
2624.7
11030.1
15009.7
d)
Cost overrun
2222.1
2347.6
1567.4
1825.3
1819.5
993.7
-15.5
-78.0
1081.8
1357.4
10.
Power
a)
Number of projects
23
23
22
20
19
15
11
12
11
12
b)
Original estimate
13717.5
14555.2
14459.6
9710.0
10233.3
9143.9
8670.5
11445.9
9985.1
7872.3
c)
Now anticipated
35470.5
30692.6
32023.3
22552.1
23456.5
24646.3
22920.6
28176.9
24005.8
21545.4
d)
Cost overrun
21753.0
16137.4
17563.7
12842.1
13223.2
15502.4
14250.1
16731.0
14020.7
13673.1
11.
Railways
a)
Number of projects
25
28
37
20
27
27
25
20
24
28
b)
Original estimate
4808.6
5012.5
5380.5
3726.1
5254.8
7909.8
7038.9
6690.1
8036.4
9282.4
c)
Now anticipated
10766.8
11452.3
11429.6
6322.8
8443.8
12431.6
12171.8
10336.9
12472.1
14042.8
d)
Cost overrun
5958.1
6439.8
6049.0
2596.8
3189.0
4521.8
5132.9
3646.8
4435.7
4760.4
12.
Surface transport
a)
Number of projects
5
9
16
20
18
17
16
6
44
53
b)
Original estimate
925.0
1867.3
2990.4
3666.2
3256.9
3326.4
3078.8
898.3
10656.5
12583.9
c)
Now anticipated
1197.6
2359.5
3864.2
5362.0
5216.6
5290.5
5847.7
1809.8
11362.9
27589.4
d)
Cost overrun
272.7
492.2
873.7
1695.9
1959.8
1964.1
2768.9
911.5
706.4
15005.5
13.
Telecommunication
a)
Number of projects
0
0
0
2
0
2
1
0
0
1
b)
Original estimate
0
0
0
465.6
0
730.8
546.0
0
0
147.0
c)
Now anticipated
0
0
0
671.9
0
730.8
546.0
0
0
147.0
d)
Cost overrun
0
0
0
206.3
0
0
0
0
0
0
14.
Others
a)
Number of projects
0
0
0
0
0
0
0
1
1
1
b)
Original estimate
0
0
0
0
0
0
0
4860.0
4860.0
4860.0
c)
Now anticipated
0
0
0
0
0
0
0
8800.0
8800.0
10571.0
d)
Cost overrun
0
0
0
0
0
0
0
3940.0
3940.0
5711.0
Total
a)
Number of projects
83
98
119
111
113
102
65
49
95
112
b)
Original estimate
38997.4
42873.6
58839.9
56556.6
58293.1
52599.3
25530.3
31414.5
51619.1
51493.0
c)
Now anticipated
79003.9
78395.1
95855.3
87297.5
88394.5
82501.2
48904.5
56780.0
79293.5
92344.3
d)
Cost overrun
40006.4
35521.5
37015.4
30740.9
30101.4
29901.9
23374.2
25365.5
27674.4
40851.3
Note
: 1. Data relate to central sector projects costing Rs.100 crore and above.
2. Projects without date of commissioning are not considered.
3. Cost overrun is taken as the difference between the 'anticipated cost' and the 'original cost'.
Source
: Ministry of Statistics and Programme Implementation, Government of India.
Top
Back to previous page