Click here to Visit the RBI’s new website

Tenders Awarded

Tender numberRBI/PD-Central Office Department/Others/31/24-25/ET/919
Date of publication of NITFeb 12, 2025
Nature of workSupply, Installation, Testing and Commissioning (SITC) of Centralized Air Conditioning System for Bank’s Central Office Building at Fort, Mumbai
Mode of tender enquiryE Tender
Type of bidding (single/two bid system)Two Bid System
Last date of receipt of tenderApr 04, 2025
Number of tenders received5 (Five)
Nos. and names of parties qualified after technical evaluation 4 (Four)
1. M/s Pragmatic HVAC Engineers Pvt. Ltd.
2. M/s Bluestar Ltd.
3. M/s Voltas Ltd.
4. M/s Brite Industries.
Nos. and names of parties not qualified after technical evaluation 1 (One)
1. M/s VAV Air conditioning.
Commercial Bid Ranking, if any-
Final Ranking, if any-
Whether contract awarded to lowest tenderer/evaluated L1Yes
Contract number and datePrem.COBM.Cell No.S 333/08.31.012/2025-26 dated Jul 09, 2025
Name of contractorM/s. Bluestar Ltd.
Value of contract
Sr.No. Description Amount
a Total Capital Cost ₹4,18,64,789/-
b Rebate for dismantling and taking away the existing old equipment under buyback scheme ₹48,84,992/-
c All-inclusive CAMC Charges for new Air Conditioning system ₹20,79,112/-
d Charges for providing service for day-to-day operation and routine maintenance of entire new system by rendering services of the AC operators (semi-skilled) ₹21,83,004/-
e All-inclusive CAMC charges for existing 3 nos. chillers, each of capacity 300 TR (Make: Kirloskar McQuay Model: WSC 079) inclusive of all spare parts, consumables and labor for servicing and repairs ₹8,49,600/-
Scheduled date of completion of supplies 26 weeks, which shall be reckoned from the 14th day from July 09, 2025.
Actual date of start of work -
Actual date of completion of work -
Reasons for delay, if any-