| Tender number | RBI/Central Office/Premises Department/11/20-21/ET/401 |
| Date of publication of NIT | Jan 02, 2021 |
| Nature of work | Design, Fabrication, Supply and Fixing factory made Modular Work Stations, Cabin Partitions, Cabin Work tables & associated utilities / accessories for Reserve Bank of India at 13th Floor (in E wing) & 20th Floor (in F wing) of Maker Tower near Cuffe Parade, Mumbai |
| Mode of tender enquiry | E-tender (Open) |
| Type of bidding (single/two bid system) | Two Bid System |
| Last date of receipt of tender | Feb 02, 2021 |
| Number of tenders received | 5 (Five) |
| Nos. and names of parties qualified after technical evaluation | 4 (Four) (i) M/s Adarsh Infrainterior Pvt. Ltd.
(ii) M/s Durian Industries Ltd.
(iii) M/s Eurocoustic Products Ltd.
(iv) M/s Nutech Office System Pvt. Ltd. |
| Nos. and names of parties not qualified after technical evaluation | 1(One) (i) M/s Bhavik Systems Pvt. Ltd. |
| Commercial Bid Ranking, if any | - |
| Final Ranking, if any | - |
| Whether contract awarded to lowest tenderer/evaluated L1 | Yes |
| Contract number and date | Prem.TD.No.S 48/03.41.113/2021-22 dated Jun 01, 2021 |
| Name of contractor | M/s Eurocoustic Products Ltd |
| Value of contract | ₹1,24,37,350/- |
| Scheduled date of completion of supplies | 120 calendar days from 15th day of the date of issue of work order |
| Actual date of start of work | Jun 16, 2021 |
| Actual date of completion of work | Nov 15, 2021 |
| Reasons for delay, if any | COVID-19 pandemic induced restrictions / lockdowns |