Corrigendum dated December 11, 2020 Corrigendum dated December 01, 2020 e-Tender No. RBI/RBSC//288/20-21/ET/288 The captioned meeting was held at 11:30 a.m. on November 18, 2020 at the Seminar Hall, RBSC, Chennai. The meeting was chaired by Shri N. Senthil Kumar, Director (Gr. ‘E’) and the undernoted Officers/ Staff attended the meeting: -
Shri Sunil M. R., Manager (Estate Cell) -
Shri Godwin Justin, Assistant Manager (Estate Cell) -
Shri Rajeev S. J., Junior Engineer (Electrical) Representative from M/s. Enseigner Pvt. Ltd. attended the meeting. Clarification to the query raised by the vendor in the meeting is as below: Sl. No. | Query Raised | Clarifications by RBSC | 1. | Is it compulsory to provide redundant CPU as per tender Annexure II? | Yes. It is required to provide redundant CPU as per tender conditions. | The Chief General Manager/ Principal Reserve Bank Staff College 359, Anna Salai Teynampet Chennai – 600 018 November 20, 2020 | |