Minutes of Pre Bid meeting - Annual Maintenance Contract for operation and routine maintenance of Central AC Plant and Associated Equipment at Bank’s Main Office Building, 8-9, Vipin Khand, Gomti Nagar, Lucknow

Corrigendum - Extension of Last Date of Submission dated May 20, 2022

Corrigendum - Extension of Last Date of Submission dated May 06, 2022

Corrigendum - Extension of Last Date of Submission dated April 22, 2022

Minutes of Pre Bid meeting - Annual Maintenance Contract for operation and routine maintenance of Central AC Plant and Associated Equipment at Bank’s Main Office Building, 8-9, Vipin Khand, Gomti Nagar, Lucknow-226010

Pre bid meeting was conducted on 11 Apr 2022 at 1100 hrs. Queries raised by the firms are as follows:

S. No. Firm’s Name Query / Suggestion by the firm Bank’s Remarks
1. Sterling and Wilson Pvt. Ltd. Estimated cost of ₹.9.90 Lakhs is with or without taxes Cost is including of all taxes as mentioned in the tender part I section II para 1.
2. Sterling and Wilson Pvt. Ltd. Waving off of Bank’s solvency certificate clause Firm has been advised to follow the tender terms and conditions
3. Sterling and Wilson Pvt. Ltd. Applicability of taxes and duties are as per State Govt. / Central Govt. / Local Bodies Firm has been advised to follow the tender terms and conditions
4. Sterling and Wilson Pvt. Ltd. Time extension for submission of BG from 15 days to 30 days Firm has been advised to follow the tender terms and conditions
5. Sterling and Wilson Pvt. Ltd. Clarification on consumable materials Firm has been advised to follow the tender terms and conditions
6. Sterling and Wilson Pvt. Ltd. Cost for additional manpower supply Firm has been advised to follow the tender terms and conditions
7. Sterling and Wilson Pvt. Ltd. Working hours for the manpower deputed at site 08 hours a day and as per Bank’s requirement
8. Sterling and Wilson Pvt. Ltd. Elaborate the restricted hours Non-Banking hours (Before 09:00 AM and After 06:00 PM) are the restricted hours
9. Sterling and Wilson Pvt. Ltd. Supply cost of materials for repair works Advised firm that the material cost will be as per market rates with contractor’s profit
10. ETA Engineering Pvt. Ltd. Scope of condenser descaling work Separate contract will be done with the OEM / Equipment integrator for condenser descaling and system inspection work.
11. ETA Engineering Pvt. Ltd. Firms should have adequate presence in Lucknow/ Kanpur by way of office establishment, and authorized personnel Firms should have adequate presence in Lucknow/ Kanpur/ Delhi (NCR) by way of office establishment and authorized personnel