Corrigendum - Supply, Installation, Testing and Commissioning of 2x250 KVA Diesel Generator (DG) Sets at Reserve Bank Staff College, Anna Salai, Teynampet, Chennai

Corrigendum dated August 28, 2020

Extension of Last Date for Submission dated August 14, 2020

Corrigendum dated July 30, 2020

Extension of Last Date for Submission dated July 28, 2020

E-Tender No. RBI//RBSC//6/20-21/ET/6

Sr. No. Page No Clause No. RBI TENDER PARA Query received by e-Mail RBSC’s Clarification
1 17 20.e DG set will be tested on load of unity power factor for the rated KW rating. During testing, each of the D.G. Set covered under scope of work, shall be operated for a period of 12 hours on the rated KW at DG set’s KW rating which includes one hour on 10% overload after continuous run of the 11Hours. As per manufacturers standard testing will be offered at factory for 1Hour including 10 minutes over load testing and maximum they will allow for 8 Hrs. Please confirm. DG set shall be operated for a period of 4 hours on the rated KW at DG set’s KW rating which includes one hour on 10% overload after continuous run of the 3 hours.
2 18 22 Performance Bank Guarantee(BG) BG will be submitted for the period for Defect Liability period i.e. for 01 year from the date of virtual completion. However the warranty of DG set is subject to proper maintenance of DG set as per manufacturer’s recommendation, hence submission of performance BG for 10 years is not possible. Please confirm. DG set will be under AMC on completion of DLP and the AMC will be with the supplier. Hence, DG sets will be invariably maintained as per manufacturers recommendations.
There will be no change in Bank Guarantee clause.
3 19 24.f Clearance/ Approval of the complete installation from CPCB/state pollution control Board/CEI This DG sets having product approval certificate of CPCB approved nominee (ARAI). Hence separate NOC from CPCB is not required. We will Provide CEI approval. Please Confirm. Necessary supporting documents shall be submitted for our scrutiny and approval
4 43 4 Period of completion 8 weeks It will take 4 weeks for drawing approval of DG, 4 weeks for manufacturing of DG and 4 weeks for Installation. Hence we request you to give us the completion period approval of 12 weeks. Period of completion is changed to 12 weeks as desired.
5 46 6 Microprocessor based AMF panel This DG set having a microprocessor based DG set controller cum-AMF relay as a part of DG set, hence separate AMF relay is not required hence we are not considering. Please confirm. If the DG set comes with in- built DG set controller and AMF relay, separate AMF relay is not required. However, panel shall be supplied with other components as per tender provisions.

Chief General Manager/Principal
Reserve Bank Staff College
Chennai

July 13, 2020