Minutes of Pre-bid Meeting - Design, Supply, Installation, Testing and Commissioning of Roof Top Grid Interactive 100 KWp SPV based Solar Power System for Bank's Office Building at CBD, Belapur

(e-tender no. RBI/Belapur/Estate/57/19-20/ET/145)

A pre-bid meeting in respect of the captioned tender was held as per schedule on October 31, 2019 at 11.00 am. Queries raised during the meeting and clarifications are as follows:

Sr No. Queries Bank’s Comments
1 Regarding Model Mounting Structure, Height is not mentioned. The height of PV Module mounting structure may be of any suitable height such that the minimum guaranteed generation as specified in the tender document can be achieved.
2 For Net Metering, Request to share Electricity Bill. Details will be made available on site.
3 Regarding EMD exemption for MSME vendors. MSMEs are Exempted from providing the EMD.
4 Regarding Service Setup. Our Office is in Nashik. Is it okay? Nashik is acceptable.
5 Is it including of Net metering connectivity completion period of 3 months? Net Metering in PQ works is not mandatory. The PQ works can also be for DSITC of Grid Interactive Solar Power system without net metering.

Entire work, as per the scope of work including the net-metering, is required to be completed in the stipulated time period of 12 weeks.
6 For monitoring system SCADA is compulsory or RMS will be okay? The software (Plant Manager & PC for remote monitoring through LAN) and hardware except PC, required for interfacing the system are to be provided by bidder.
7 At the time of quote Standard SLD to be provided or CAD drawing? Standard SLD shall be submitted by the bidder at the time of quoting for the tender.
8 Is Lightning Arrester to be provided?
If yes, please provide specifications.
The bidder shall provide the lightening arrestor including all the equipment /system (conforming to latest BIS) necessary for the protection of the solar power system against lightening.
9 Please provide Net meter process time-period. Entire work, as per the scope of work including the net-metering, is required to be completed in the stipulated time period of 12 weeks.
10 Need some Document for the accuracy of bid:
1) Energy Meter details
2) Injection Point for the length of AC cable.
3) Electricity Bill

1) May be checked on site as per required basis.
2) As per specification of the tender and site -requirement.
3) Details will be made available on website.
11 Is Net metering to be completed within 120 days? Entire work, as per the scope of work including the net-metering, is required to be completed in the stipulated time period of 12 weeks.
12 Page no. 73 (v) Annexure A calls for 155 KWp, what is the intended purpose for this? (considering Tender is for 100 KWp) At page no. 73 (v) para, the capacity of the solar power system may be read as 100 KWp instead of 155 KWp.
13 What do you mean by the term Virtual completion? The bidder may refer to para 21 at page no.44.
14 We would request you to give relaxation to MSME/Start up for years of experience. To bring down years of experience from 5 years to 3 years. Exempted as requested.
15 The Net metering came into existence from 2015 in Maharashtra. Hence, the minimum experience of 5 years cannot be applicable. The net metering should be according to the scheme which is running at the time.
16 BOQ will contain GST. Hence uniformity in GST matters. Percentage to be fixed or keep the Amount exclusive of GST. The amount shall be quoted as per the format of the Price Bid (Tender Part – II)
17 For Modbus, Wifi will be provided from whom? If vendor is providing wifi then who will do the billing. Wi-Fi is not required to be provided. However, the monitoring system is required to be provided as per tender specification.
18 Is Net metering should be according to the scheme which is running at that time? The net metering should be according to the scheme which is running at the time.